Miri Septic Sludge Treatment Plant

 

Miri Septic Sludge Treatment Plant


NINTH MALAYSIA PLAN PROJECTS

PROJECT

Project Title :


(A) Miri Septic Sludge Treatment Plant


Project Background :

All septic tanks need to be desludged regularly in order to function efficiently. The current practice in Miri is to desludge the septic tank when it is full or blocked. There is also no proper septic sludge treatment facility. The sludge collected from the septic tanks is currently being discharged to drying beds at old Lutong Landfill.

The proposed Plant is located on an 18-acre forested site at Tudan, Miri. It is about 10 km from Miri City and 4.5 km from the nearest residential area, which is Bandar Baru Permy Jaya.

The Plant shall receive and treat the septic sludge collected within Miri City and its outskirts. The treated sludge shall be disposed to Bekenu Sanitary Landfill. This is to enable the regular desludging of the septic tanks and package wastewater treatment units in Miri, thus improving the efficiency of the wastewater treatment facilities in Miri.

The capacity of this Plant is designed to cater for the projected number of septic tanks and package wastewater treatment units in Miri City up to year 2020. Based on the Sungai Miri Environmental Management Study Report, by the year 2010, there will be 30,000 units of septic tanks and hence by 2020 the total of septic tanks is estimated at 40,000 units.

 

Project Components :

The Septic Sludge Treatment Plant consists of:
 
i. Incoming Sludge Reception
ii. Sequencing Batch Reactor Aerobic Digester (SBR Tank)
iii. Sludge Holding Tank
iv. Dewatering House (Thickening, Dewatering & Polymer Dosing System)
v. Control Room
vi. Wetland/Lagoon

The supporting buildings consist of:
 
i. Administration Office and Workshop
ii. Mechanical & Electrical Building
iii. Guard House
 

PROJECT GALLERY

 
administration Building Genset Room Incoming Sludge Pump Sump
Administration
Building
Genset
Room
Incoming Sludge
Pump Sump
sludge Holding Tank Sequencing Batch Reactors Tank Air Blower Room
Sludge Holding
Tank
Sequencing Batch
Reactor Tanks
Air Blowers
Room
 

PROJECT COST
RM20 Million

CONTRACTOR
Eastbourne Corporation Berhad

CONSULTANT
Konsortium Malaysia

CONTRACT PERIOD
18 months

COMMENCEMENT DATE
28 May 2009

REVISED COMPLETION DATE
26 July 2011

PRACTICAL COMPLETION DATE
9 May 2012

 

PROJECT

Project Title :

(B) Permanent Access Road for Miri Septic Sludge Treatment Plant (Continuation Project RMK-10)


Project Background :

A permanent access road is proposed to connect the Plant directly to the proposed Pujut Link which is currently under construction by Public Works Department.


Project Objective :
This proposed access road will shorten the distance to the Plant.


Project Component :
Total length of access road : 2,340 m
Width of embankment : 13.00 m
Width of carriageway : 7.40 m
Length of earth drain : 4,680 m


Number and size of culvert :
 
No. Culvert Type Length (m) Size
1 RC Box 12.00 2m x 2m
2 Reinforced Concrete Pipe 13.68 1.5 m Ɵ
3 Reinforced Concrete Pipe 12.16 1.5 m Ɵ
4 Reinforced Concrete Pipe 13.68 1.5 m Ɵ

Stone base
   
  •  Crushed rock aggregate roadbase
  •  Crushed rock aggregate subbase
:
:
250 mm thick
350 mm thick
Premix    
  • Binder Course
: 50 mm thick



PROJECT GALLERY
Locality Map
  

PROJECT COST
RM5.00 Million


CONTRACTOR
Eastbourne Corporation Berhad


CONSULTANT
Konsortium Malaysia


CONTRACT PERIOD
10 months


COMMENCEMENT DATE
25 April 2012


REVISED COMPLETION DATE
5 March 2013


PRACTICAL COMPLETION DATE
31 May 2013