Sri Aman-Betong Septic Sludge Treatment Plant
ELEVENTH MALAYSIA PLAN PROJECTS |
PROJECT
Project Title :
Sri Aman - Betong Septic Sludge Treatment Plant
Project Background :
All septic tanks need to be desludged regularly in order to maintain treatment efficiency. The current practice in Betong and Sri Aman is to desludge the septic tank when it is full or blocked. There is also no proper septic sludge treatment facility. The sludge collected from septic tanks is currently being disposed in dump sites.
The proposed septic sludge treatment plant is located on an 8 acre site next to existing Betong Landfill. It is about 5 km from Betong Town center along Jalan Lidong and 4 km from the nearest residential area.
The plant shall receive and treat septic sludge collected from the septic tanks within Betong town and its outskirts. The treated sludge shall be disposed on site. This will enable the regular desludging of the septic tanks and package wastewater treatment units in Betong. This will improve the efficiency of the wastewater treatment facilities in Betong.
This treatment plant is designed to have an ultimate capacity of 100 m3/day.
The proposed septic sludge treatment plant is located on an 8 acre site next to existing Betong Landfill. It is about 5 km from Betong Town center along Jalan Lidong and 4 km from the nearest residential area.
The plant shall receive and treat septic sludge collected from the septic tanks within Betong town and its outskirts. The treated sludge shall be disposed on site. This will enable the regular desludging of the septic tanks and package wastewater treatment units in Betong. This will improve the efficiency of the wastewater treatment facilities in Betong.
This treatment plant is designed to have an ultimate capacity of 100 m3/day.
Project Components :
- Operations Building,
- Sludge Reception and Holding Tank,
- Dewatering Building,
- Waste Water Treatment Unit,
- Polishing Ponds, and
- Landfill
Project Gallery
Satellite Map | Locality Map |
Project Cost
RM15 Million
Design Stage
Consultants | ||
No. | Field of Consultancy | Consultant's Name |
1. | Civil and Structural | Jurutera Adda Sdn. Bhd. |
2. | Mechanical and Electrical | Konsortium Bumi Consultants and Services Sdn. Bhd. |
3. | Land Surveyor | LS Survey Consultant Sdn. Bhd. |
Design Period | : | 12 months |
Schedule | : | January 2017 to December 2017 |
Progress | : | 100% |
Tendering Stage (Planned Period = 3 months)
Schedule | : | September 2024 |
Construction Stage
Contractor | : | To be apointed |
Contract Period | : | 15 months |
Schedule | : | - |