Sistem Saluran Pembetungan Najis Utama Bintulu
NINTH MALAYSIA PLAN PROJECTS
PROJECT(A) Sistem Saluran Pembetungan Najis Utama Bintulu
Project Background:
Bintulu is the only major urban center of Sarawak having a centralized sewerage system. The system was constructed in early 1980’s.
Bintulu is experiencing rapid urbanisation. New residential areas are continuously being developed together with the redevelopment of the exisiting commercial center. It is now critical to extend the main public sewer lines to the newly developed and redeveloped areas covering the existing commercial center and the old airport area.
Sewerage Services Department Sarawak has appointed Bintulu Development Authority as the implementing agency. Jurutera Wahba Sdn Bhd has been engaged as the engineering consultant.
Project Component :
The Project is for the construction of the trunk sewer as well as the sewer reticulation system for Bintulu CBD which includes all the existing shop houses, old airport and kampung areas.The sewage shall flow by gravity to existing oxidation pond at Tg. Batu.
The works shall include:
(i) Gravity flow sewer reticulation system connecting to the existing CBD sewer pipes:
a. Sewer line 225mm dia. VCP (1622m)
b. Sewer line 300mm dia. VCP (1041m)
c. Sewer line 375mm dia. VCP (170m)
d. Sewer line 450mm dia. VCP (915m)
(ii) A new intermediate pumping station
(iii) Pumping Mains (300mm dia. DI-241m) across Jalan Tun Ahmad Zaidi
PROJECT GALLERY
Pumping Station |
Manhole (Behind Shophouses) |
Manhole (Main Sewer) |
Layout Plan of Proposed Bintulu Trunk Sewer System |
RM10 Million
CONTRACTOR
Pembinaan Kuantiti Sdn. Bhd.
CONSULTANT
Jurutera Wahba Sdn. Bhd.
CONTRACT PERIOD
18 months
COMMENCEMENT DATE
23 February 2010
REVISED COMPLETION DATE
20 March 2012
PROGRESS AS AT 31 JANUARY 2013
100%
PROJECT
(B) Sistem Saluran Pembetungan Najis Utama Bintulu (Continuation Project RMK-10)
Project Background
The existing sewer line shall be extended to cover the areas around Jalan Tun Ahmad Zaidi, JA-Drain and Medan Jaya. The sewage shall be channel to the existing Oxidation Pond at Jalan Tun Ahmad Zaidi.
Project Objective
This Project aims to increase the sewerage coverage for Bintulu Town.
Project Component
Population equivalent (PE) served | 5,650 PE |
No. of properties connected | 660 nos. |
Length of sewer
|
Approximately 2.5 km (under survey & design) |
No. of pump stations | (under survey & design) |
PROJECT GALLERY
Locality Map |
PROJECT COST
RM3.05 Million
CONTRACTOR
H.K.K and Salem Construction Sdn Bhd
CONSULTANT
KTA (Sarawak) Sdn Bhd
CONTRACT PERIOD
12 Months
COMMENCEMENT DATE
14 February 2013
COMPLETION DATE
13 February 2014
PROGRESS AS AT 31 JULY 2015
100%