picture

Sistem Saluran Pembetungan Najis Utama Bintulu

 

Sistem Saluran Pembetungan Najis Utama Bintulu


NINTH MALAYSIA PLAN PROJECTS

PROJECT

(A) Sistem Saluran Pembetungan Najis Utama Bintulu

Project Background:

Bintulu is the only major urban center of Sarawak having a centralized sewerage system. The system was constructed in early 1980’s.

Bintulu is experiencing rapid urbanisation. New residential areas are continuously being developed together with the redevelopment of the exisiting commercial center. It is now critical to extend the main public sewer lines to the newly developed and redeveloped areas covering the existing commercial center and the old airport area.

Sewerage Services Department Sarawak has appointed Bintulu Development Authority as the implementing agency. Jurutera Wahba Sdn Bhd has been engaged as the engineering consultant.


Project Component :

The Project is for the construction of the trunk sewer as well as the sewer reticulation system for Bintulu CBD which includes all the existing shop houses, old airport and kampung areas.The sewage shall flow by gravity to existing oxidation pond at Tg. Batu.

The works shall include:

(i) Gravity flow sewer reticulation system connecting to the existing CBD sewer pipes:
a. Sewer line 225mm dia. VCP (1622m)
b. Sewer line 300mm dia. VCP (1041m)
c. Sewer line 375mm dia. VCP (170m)
d. Sewer line 450mm dia. VCP (915m)

(ii) A new intermediate pumping station

(iii) Pumping Mains (300mm dia. DI-241m) across Jalan Tun Ahmad Zaidi

 

 

PROJECT GALLERY
Pumping
Station
Manhole
(Behind Shophouses)
Manhole
(Main Sewer)
Layout Plan of Proposed Bintulu Trunk Sewer System

PROJECT COST
RM10 Million

CONTRACTOR
Pembinaan Kuantiti Sdn. Bhd.

CONSULTANT
Jurutera Wahba Sdn. Bhd.

CONTRACT PERIOD
18 months

COMMENCEMENT DATE
23 February 2010

REVISED COMPLETION DATE
20 March 2012

PROGRESS AS AT 31 JANUARY 2013
100%

 

PROJECT

(B) Sistem Saluran Pembetungan Najis Utama Bintulu (Continuation Project RMK-10)

Project Background
The existing sewer line shall be extended to cover the areas around Jalan Tun Ahmad Zaidi, JA-Drain and Medan Jaya. The sewage shall be channel to the existing Oxidation Pond at Jalan Tun Ahmad Zaidi.

Project Objective

This Project aims to increase the sewerage coverage for Bintulu Town.

Project Component
 Population equivalent (PE) served   5,650 PE
 No. of properties connected   660 nos.
 Length of sewer
  • 225 dia VCP

  • 300 dia DI

  • 400 dia VCP
  Approximately 2.5 km (under survey & design)
 No. of pump stations   (under survey & design)
 

 

PROJECT GALLERY
 
Bintulu Locality Map
Locality Map

 

PROJECT COST
RM3.05 Million

CONTRACTOR
H.K.K and Salem Construction Sdn Bhd

CONSULTANT
KTA (Sarawak) Sdn Bhd

CONTRACT PERIOD
12 Months

COMMENCEMENT DATE
14 February 2013

COMPLETION DATE
13 February 2014

PROGRESS AS AT 31 JULY 2015
100%