Limbang Septic Sludge Treatment PlantLimbang Septic Sludge Treatment Plant
ELEVENTH MALAYSIA PLAN PROJECTS

PROJECT Project Title :
Limbang Septic Sludge Treatment Plant


Project Background :

All septic tanks need to be desludged regularly in order to maintain treatment efficiency. The current practice in Limbang town is to desludge the septic tank when it is full or blocked. There is also no proper septic sludge treatment facility. The sludge collected from septic tanks is currently being disposed in dump sites.  

The proposed septic sludge treatment plant is located on an 11-acre site about 10 km from Limbang Town center along Jalan Kubong. It is about 0.5 km from the nearest residential area. 

The plant shall receive and treat septic sludge collected from the septic tanks within Limbang town and its outskirts. The treated sludge shall be disposed on site. This will enable the regular desludging of the septic tanks and package wastewater treatment units in Limbang. This will improve the efficiency of the wastewater treatment facilities in Limbang.

This treatment plant is designed to have an ultimate capacity of 100 m3/day.


Project Components :
  1. Operations Building,
  2. Sludge Reception and Holding Tank,
  3. Dewatering Building,
  4. Waste Water Treatment Unit,
  5. Polishing Ponds, and
  6. Landfill

Project Gallery
  Satellite Map Limbang SSTP   Locality Map Limbang  
  Satellite Map
  Locality Map
 

Project CostRM15 Million

Design Stage
Consultants
No. Field of Consultancy Consultant's Name
1. Civil and Structural Standard Engineers Sdn Bhd
2. Mechanical and Electrical Jurutera Azan Bersekutu Sdn Bhd
3. Land Surveyor Survey Development Services

Design Period
: 9 months
Schedule : September 2017 to May 2018
Progress as at 30.4.2019
: 100%


Tendering Stage (Planned Period = 3 months)
Schedule : 2019


Construction Stage
Contractor : To be appointed
Planned Period : 15 months
Schedule : -