Sarikei-Bintangor Septic Sludge Treatment PlantSarikei-Bintangor Septic Sludge Treatment Plant
ELEVENTH MALAYSIA PLAN PROJECTS

PROJECT Project Title :
Sarikei-Bintangor Septic Sludge Treatment Plant


Project Background :

All septic tanks need to be desludged regularly in order to maintain treatment efficiency. The current practice in Sarikei and Bintangor town is to desludge the septic tank when it is full or blocked. There is also no proper septic sludge treatment facility. The sludge collected from septic tanks is currently being disposed in dump sites.  

The proposed septic sludge treatment plant is located on an 8-acre site about 6 km from Sarikei Town center and 10 km from Bintangor Town center along Jalan Sarikei-Bintangor Bypass. It is about 2 km from the nearest residential area. 

The plant shall receive and treat septic sludge collected from the septic tanks within Sarikei-Bintangor town and its outskirts. The treated sludge shall be disposed on site. This will enable the regular desludging of the septic tanks and package wastewater treatment units in Sarikei and Bintangor. This will improve the efficiency of the wastewater treatment facilities in the two towns.

This treatment plant is designed to have an ultimate capacity of 100 m3/day.


Project Components :
  1. Operations Building,
  2. Sludge Reception and Holding Tank,
  3. Dewatering Building,
  4. Waste Water Treatment Unit,
  5. Polishing Ponds, and
  6. Landfill

Project Gallery
  Satellite Map Sarikei Bintangor   Sarikei Bintangor SSTP  
  Satellite Map
  Locality Map
 
Project CostRM15 Million

Design Stage
Consultants
No. Field of Consultancy Consultant's Name
1. Civil and Structural Jurutera CMP (Sarawak) Sdn Bhd
2. Mechanical and Electrical Perunding UZL Sdn Bhd
3. Land Surveyor Resources Surveys Services

Design Period
: 9 months
Schedule : September 2017 to May 2018
Progress as at 30.4.2019
: 100%


Tendering Stage (Planned Period = 3 months)
Schedule : 2019


Construction Stage
Contractor : To be appointed
Planned Period : 15 months
Schedule : -