Miri City Wastewater Management System Master Plan StudyMiri City Wastewater Management System Master Plan Study
NINTH MALAYSIA PLAN PROJECTS

PROJECT
Project Title :
Miri City Wastewater Management System Master Plan Study
Project Background :

Miri has a population of 200,000. The city is situated on the coastline fronting South China Sea. It has no centralized sewerage system. The black water is treated by individual septic tanks. The grey water is discharged directly into the waterways. Due to the population increase, the drains in the built-up area are seriously polluted.

The project is to carry out a study on the wastewater management to formulate the long-term management and technical strategies to collect, transport, treat and dispose the wastewater of the city.

The study shall formulate a master plan for wastewater management that shall provide the necessary framework guiding the future wastewater infrastructure development of the city and prioritizing the strategies for implementation.

Final Master Plan Report: Executive Summary Final Master Plan Report Volume 1: Main Report Final Master Plan Report Volume 2: Appendices


Project CostRM2 Million

ConsultantsEngineering and Environmental Consultant Sdn Bhd / Jurutera Minsar Consult Sdn. Bhd / KTA (Sarawak) Sdn. Bhd.

Contract Period10 months

Commencement Date5 May 2008

Actual Completion Date17 March 2010

Progress  Final Report Submitted