Miri Septic Sludge Treatment PlantMiri Septic Sludge Treatment Plant
NINTH MALAYSIA PLAN PROJECTS

PROJECTProject Title :

(A) Miri Septic Sludge Treatment Plant

Project Background :

All septic tanks need to be desludged regularly in order to function efficiently. The current practice in Miri is to desludge the septic tank when it is full or blocked. There is also no proper septic sludge treatment facility. The sludge collected from the septic tanks is currently being discharged to drying beds at old Lutong Landfill.

The proposed Plant is located on an 18-acre forested site at Tudan, Miri. It is about 10 km from Miri City and 4.5 km from the nearest residential area, which is Bandar Baru Permy Jaya.

The Plant shall receive and treat the septic sludge collected within Miri City and its outskirts. The treated sludge shall be disposed to Bekenu Sanitary Landfill. This is to enable the regular desludging of the septic tanks and package wastewater treatment units in Miri, thus improving the efficiency of the wastewater treatment facilities in Miri.

The capacity of this Plant is designed to cater for the projected number of septic tanks and package wastewater treatment units in Miri City up to year 2020. Based on the Sungai Miri Environmental Management Study Report, by the year 2010, there will be 30,000 units of septic tanks and hence by 2020 the total of septic tanks is estimated at 40,000 units.

Project Components :

The Septic Sludge Treatment Plant consists of:

i. Incoming Sludge Reception
ii.
Sequencing Batch Reactor Aerobic Digester (SBR Tank)
iii. Sludge Holding Tank
iv. Dewatering House (Thickening, Dewatering & Polymer Dosing System)
v. Control Room
vi. Wetland/Lagoon

The supporting buildings consist of:

i. Administration Office and Workshop
ii. Mechanical & Electrical Building
iii. Guard House


PROJECT GALLERY
administration Building Genset Room Incoming Sludge Pump Sump
Administration
Building
Genset
Room
Incoming Sludge
Pump Sump
sludge Holding Tank Sequencing Batch Reactors Tank Air Blower Room
Sludge Holding
Tank
Sequencing Batch
Reactor Tanks
Air Blowers
Room


PROJECT COSTRM20 Million
CONTRACTOREastbourne Corporation Berhad
CONSULTANTKonsortium Malaysia
CONTRACT PERIOD18 months
COMMENCEMENT DATE28 May 2009

REVISED COMPLETION DATE26 July 2011

PRACTICAL COMPLETION DATE9 May 2012


PROJECTProject Title :

(B) Permanent Access Road for Miri Septic Sludge Treatment Plant (Continuation Project RMK-10)

Project Background :

A permanent access road is proposed to connect the Plant directly to the proposed Pujut Link which is currently under construction by Public Works Department.

Project Objective :
This proposed access road will shorten the distance to the Plant.

Project Component :
Total length of access road : 2,340 m
Width of embankment : 13.00 m
Width of carriageway : 7.40 m
Length of earth drain : 4,680 m

Number and size of culvert :

No. Culvert Type Length (m) Size
1 RC Box 12.00 2m x 2m
2 Reinforced Concrete Pipe 13.68 1.5 m Ɵ
3 Reinforced Concrete Pipe 12.16 1.5 m Ɵ
4 Reinforced Concrete Pipe 13.68 1.5 m Ɵ

Stone base
   
  •  Crushed rock aggregate roadbase
  •  Crushed rock aggregate subbase
:
:
250 mm thick
350 mm thick
Premix    
  • Binder Course
: 50 mm thick


PROJECT GALLERY
Locality Map


PROJECT COSTRM5.00 Million

CONTRACTOREastbourne Corporation Berhad

CONSULTANTKonsortium Malaysia

CONTRACT PERIOD10 months

COMMENCEMENT DATE25 April 2012

REVISED COMPLETION DATE5 March 2013

PRACTICAL COMPLETION DATE31 May 2013